GAS Β· ERCOTNRG THW GT 138
NRG THW GT 138 is a 456 MW gas request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0479
- Grid region
- ERCOT (Texas)
- Developer
- NRG THW GT LLC
- Connection point (POI)
- 138 kV Bus Number: 45515, Bus Name: T_H_W__POI_8
- Technology
- Gas: 456 MW
- Total requested
- 456 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 22 November 2022
- Proposed online date
- June 2026
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem