United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2016 requests) โ€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,194150.9 GW
Active in queue25.8 GW162 requests
Agreement signed18.1 GW106 requests
Withdrawn1,194150.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,194 requests ยท page 5 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-496, Pulaski County
Solar
200 MWWithdrawn / abandoned Pulaski, GASoutheast Sep 2016
Onshore wind project GEN-2016-108, Mercer County
Onshore wind
200 MWWithdrawn / abandoned Mercer, NDSPP Nov 2016target 2019
Solar project G0545, Klamath County
Solar
200 MWWithdrawn / abandoned Klamath, ORWest Jun 2016target 2019
Onshore wind project GI-59, Osage County
Onshore wind
200 MWWithdrawn / abandoned Osage, OKSoutheast Aug 2016target 2018
Solar project Q240, Pinal County
Solar
200 MWWithdrawn / abandoned Pinal, AZWest Mar 2016target 2019
Solar project IC-542, Toombs County
Solar
200 MWWithdrawn / abandoned Toombs, GASoutheast Nov 2016
Solar + storage project 788, Emery County
Solar + storage
200 MWWithdrawn / abandoned Emery, UTWest Aug 2016target 2018
Charbray Solar
Solar ยท 8minutenergy
200 MWWithdrawn / abandoned Mitchell, TXERCOT Jul 2016target 2020
Onshore wind project J721, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDMISO Oct 2016target 2019
Onshore wind project J629, Deuel County
Onshore wind
200 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2019
Shorthorn 2 Solar
Solar ยท 8minutenergy
200 MWWithdrawn / abandoned Childress, TXERCOT Oct 2016target 2020
Solar project IC-490, Burke County
Solar
200 MWWithdrawn / abandoned Burke, GASoutheast Sep 2016
Onshore wind project J780, Sheridan County
Onshore wind
200 MWWithdrawn / abandoned Sheridan, NDMISO Nov 2016target 2020
Onshore wind project J747, Deuel County
Onshore wind
200 MWWithdrawn / abandoned Deuel, SDMISO Nov 2016target 2017
Solar project 756, Klamath County
Solar
200 MWWithdrawn / abandoned Klamath, ORWest May 2016target 2020
Solar project IC-472, Dougherty County
Solar
200 MWWithdrawn / abandoned Dougherty, GASoutheast Jul 2016
Onshore wind project J739, Lyon County
Onshore wind
200 MWWithdrawn / abandoned Lyon, MNMISO Nov 2016target 2020
Onshore wind project GEN-2016-056, Hockley County
Onshore wind
200 MWWithdrawn / abandoned Hockley, TXSPP Mar 2016target 2018
Solar project J670, Panola County
Solar
200 MWWithdrawn / abandoned Panola, MSMISO Jul 2016target 2019
Gateway Energy Storage 2
Battery storage
200 MWWithdrawn / abandoned San Diego, CACAISO May 2016target 2019
Onshore wind project J774, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDMISO Nov 2016target 2019
Onshore wind project J630, Deuel County
Onshore wind
200 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2019
Solar project GI-2016-13, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Jun 2016target 2020
Onshore wind project J631, Allegan County
Onshore wind
200 MWWithdrawn / abandoned Allegan, MIMISO May 2016target 2019
SP-Pecos Bend Solar A
Solar ยท Solar Prime
200 MWWithdrawn / abandoned Pecos, TXERCOT Oct 2016target 2021
Onshore wind project J599, Walworth County
Onshore wind
200 MWWithdrawn / abandoned Walworth, SDMISO May 2016target 2018
Hubbard Wind
Onshore wind ยท Nextera
200 MWWithdrawn / abandoned ERCOT May 2016target 2018
Onshore wind project 2017-G1
Onshore wind
200 MWWithdrawn / abandoned West Dec 2016target 2020
Hariana Solar
Solar ยท 8minutenergy
200 MWWithdrawn / abandoned ERCOT Dec 2016target 2021
Onshore wind project J761, Faribault County
Onshore wind
200 MWWithdrawn / abandoned Faribault, MNMISO Nov 2016target 2020
Solar project Q235, Maricopa County
Solar
200 MWWithdrawn / abandoned Maricopa, AZWest Mar 2016target 2021
Byers Wind
Onshore wind ยท Innergex
200 MWWithdrawn / abandoned ERCOT Nov 2016target 2019
Onshore wind project AB2-028, Henry County
Onshore wind
200 MWWithdrawn / abandoned Henry, INPJM Feb 2016target 2018
Onshore wind project GEN-2016-063, Johnston County
Onshore wind
200 MWWithdrawn / abandoned Johnston, OKSPP Mar 20162023
Onshore wind project GI-57, Osage County
Onshore wind
200 MWWithdrawn / abandoned Osage, OKSoutheast May 2016target 2018
Shorthorn Solar
Solar ยท 8minutenergy
200 MWWithdrawn / abandoned ERCOT Jun 2016target 2020
Onshore wind project J775, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDMISO Nov 2016target 2019
Solar project Q243, Pinal County
Solar
200 MWWithdrawn / abandoned Pinal, AZWest Mar 2016target 2019
Onshore wind project J712, Iowa County
Onshore wind
200 MWWithdrawn / abandoned Iowa, WIMISO Sep 2016target 2020
Corriente Solar
Solar ยท 8 Minute Energy
200 MWWithdrawn / abandoned ERCOT Dec 2016target 2019
Solar project Q54, Kern County
Solar
200 MWWithdrawn / abandoned Kern, CAWest Aug 2016target 2021
Solar project GI-2016-21, Lincoln County
Solar
200 MWWithdrawn / abandoned Lincoln, COWest Sep 2016target 2019
Onshore wind project GEN-2016-101, Noble County
Onshore wind
195 MWWithdrawn / abandoned Noble, OKSPP Nov 20162020
Gas project J561, Kalamazoo County
Gas
190 MWWithdrawn / abandoned Kalamazoo, MIMISO May 2016target 2017
Solar project 52, Cochise County
Solar
188 MWWithdrawn / abandoned Cochise, AZWest Dec 2016target 2018
Solar project 773, Iron County
Solar
188 MWWithdrawn / abandoned Iron, UTWest Jul 2016target 2018
Solar project 774, Iron County
Solar
188 MWWithdrawn / abandoned Iron, UTWest Jul 2016target 2018
Solar project 775, Iron County
Solar
188 MWWithdrawn / abandoned Iron, UTWest Jul 2016target 2019
Hudson Solar 1
Solar + storage
186 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2024
Ponwar Solar Farm
Solar ยท 8minutenergy
180 MWWithdrawn / abandoned Upton, TXERCOT Apr 2016target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)