United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTShorthorn 2 Solar
Shorthorn 2 Solar is a 200 MW solar request withdrawn in the ERCOT interconnection queue, in Childress County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2016 (completed)
- Withdrawn / abandonedJun 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20INR0005
- Grid region
- ERCOT (Texas)
- Developer
- 8minutenergy
- Connection point (POI)
- 60501 Tesla 345kV
- Location
- Childress County, Texas
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 25 October 2016
- Proposed online date
- October 2020
- Withdrawn
- June 2019
Location
Marker shows the centre of Childress County; the queue data does not give exact sites.
Other requests in Childress County
- Fagus Solar Park 3 SLFSolar + storage Β· 170 MW Β· agreement signed
- Fagus Solar Park 2 SLFSolar + storage Β· 167 MW Β· agreement signed
- Fagus Solar Park 1 SLFSolar + storage Β· 166 MW Β· agreement signed
- Independence Trail StorageBattery storage Β· 100 MW Β· in study
- Mars SolarSolar Β· 52.8 MW Β· suspended
- Misae SolarSolar Β· 241 MW Β· built
- Ponil SolarSolar Β· 145 MW Β· withdrawn
- Proteus Oak Forest SolarSolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem