SOLAR Β· ERCOTMisae Solar
Misae Solar is a 241 MW solar request built and operating in the ERCOT interconnection queue, in Childress County, Texas.
Request details
- Queue ID
- 18INR0045
- Grid region
- ERCOT (Texas)
- Developer
- CIP
- Connection point (POI)
- 60501 Tesla 345kV
- Location
- Childress County, Texas
- Technology
- Solar: 241 MW
- Total requested
- 241 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 19 October 2016
- Agreement signed
- 18 July 2018
- Proposed online date
- December 2021
- Came online
- December 2021
Location
Marker shows the centre of Childress County; the queue data does not give exact sites.
Other requests in Childress County
- Fagus Solar Park 3 SLFSolar + storage Β· 170 MW Β· agreement signed
- Fagus Solar Park 2 SLFSolar + storage Β· 167 MW Β· agreement signed
- Fagus Solar Park 1 SLFSolar + storage Β· 166 MW Β· agreement signed
- Independence Trail StorageBattery storage Β· 100 MW Β· in study
- Mars SolarSolar Β· 52.8 MW Β· suspended
- Shorthorn 2 SolarSolar Β· 200 MW Β· withdrawn
- Ponil SolarSolar Β· 145 MW Β· withdrawn
- Proteus Oak Forest SolarSolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem