πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR + STORAGE Β· WEST

Solar + storage project 788, Emery County

Solar + storage project 788, Emery County is a 200 MW solar + storage request withdrawn in the West interconnection queue, in Emery County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedMay 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
788
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Emery-Sigurd #2 line
Location
Emery County, Utah
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA executed 5/13/19, LGIA terminated and combined with Q0787
Queue status
Withdrawn
Entered queue
8 August 2016
Agreement signed
13 May 2019
Proposed online date
November 2018

Location

Marker shows the centre of Emery County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Emery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem