SOLAR Β· ERCOT

Ponwar Solar Farm

Ponwar Solar Farm is a 180 MW solar request withdrawn in the ERCOT interconnection queue, in Upton County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2016 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
18INR0027
Grid region
ERCOT (Texas)
Developer
8minutenergy
Connection point (POI)
tap 138kV 76032 N McCamey - 60361 Santa Rita
Location
Upton County, Texas
Technology
Solar: 180 MW
Total requested
180 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
5 April 2016
Proposed online date
June 2021
Withdrawn
March 2020

Location

Marker shows the centre of Upton County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Upton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem