🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Hudson Solar 1

Hudson Solar 1 is a 186 MW solar + storage request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedJan 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1235
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Panoche Substation 115 kV
Location
Fresno County, California
Technology
Solar: 86.6 MW · Battery: 99.0 MW
Total requested
186 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Withdrawn
Entered queue
2 May 2016
Proposed online date
December 2024
Withdrawn
January 2021

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem