πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· PJM

Onshore wind project AB2-028, Henry County

Onshore wind project AB2-028, Henry County is a 200 MW onshore wind request withdrawn in the PJM interconnection queue, in Henry County, Indiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2016 (completed)
  2. Withdrawn / abandonedJun 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB2-028
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Fall Creek-Desoto 345kV
Location
Henry County, Indiana
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
10 February 2016
Proposed online date
October 2018
Withdrawn
June 2021

Location

Marker shows the centre of Henry County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Henry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem