United States › Grid › Interconnection queues › Indiana
BATTERY STORAGE · MISOBattery storage project J3387, Henry County
Battery storage project J3387, Henry County is a 150 MW battery storage request in interconnection study in the MISO interconnection queue, in Henry County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3387
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Connersville - New Castle 138.0kV
- Location
- Henry County, Indiana
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 18 April 2024
- Proposed online date
- October 2026
Location
Marker shows the centre of Henry County; the queue data does not give exact sites.
Other requests in Henry County
- Solar project J903, Henry CountySolar · 100 MW · under construction
- Bellflower Solar 1Solar · 153 MW · built
- Onshore wind project AC2-177, Henry CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project H013, Henry CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project AB2-028, Henry CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J1031, Henry CountyOnshore wind · 150 MW · withdrawn
- Solar project J1689, Henry CountySolar · 150 MW · withdrawn
- Solar project J4008, Henry CountySolar · 150 MW · withdrawn
- Solar project J1690, Henry CountySolar · 125 MW · withdrawn
- Solar project AH1-484, Henry CountySolar · 115 MW · withdrawn
- Solar project AF2-211, Henry CountySolar · 100 MW · withdrawn
- Flat Rock - WF-1Onshore wind · 90.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem