πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

SOLAR Β· WEST

Solar project Q243, Pinal County

Solar project Q243, Pinal County is a 200 MW solar request withdrawn in the West interconnection queue, in Pinal County, Arizona, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q243
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Santa Rosa 230kV Substation
Location
Pinal County, Arizona
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
31 March 2016
Proposed online date
December 2019

Location

Marker shows the centre of Pinal County; the queue data does not give exact sites.

Power plants in Arizona Β· Transmission lines in Arizona

Other requests in Pinal County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem