Interconnection queue in MISO (Midcontinent) (2025 requests) β€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown390120.8 GW
Active in queue120.8 GW390 requests
Agreement signed180 MW1 requests
Withdrawn6222.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

390 requests Β· page 5 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3891, Pope County
Solar
200 MWIn study Pope, ARMISO Jan 2025target 2030
Solar + storage project J2265, Bollinger County
Solar + storage
200 MWIn study Bollinger, MOMISO Jul 2025target 2024
Surplus; J1434
Battery storage
200 MWIn study St. Francis, ARMISO Jun 2025target 2027
Solar + storage project J4134, Ouachita County
Solar + storage
200 MWIn study Ouachita, ARMISO Oct 2025target 2030
Solar project J3919, Lincoln County
Solar
200 MWIn study Lincoln, MOMISO Mar 2025target 2030
Solar + storage project J3981, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Battery storage project J4154, Madison County
Battery storage
200 MWIn study Madison, MSMISO Oct 2025target 2028
Replacing 200 MW of Solar with Nuclear; J1444
Nuclear
200 MWIn study Linn, IAMISO Aug 2025target 2029
Onshore wind project J2447, Murray County
Onshore wind
200 MWIn study Murray, MNMISO Oct 2025target 2027
Battery storage project J4065, Dakota County
Battery storage
200 MWIn study Dakota, MNMISO Sep 2025target 2030
Battery storage project J4053, Grand Traverse County
Battery storage
200 MWIn study Grand Traverse, MIMISO Jul 2025target 2028
Battery storage project J4030, Faulkner County
Battery storage
200 MWIn study Faulkner, ARMISO May 2025target 2029
Surplus
Battery storage
200 MWIn study Nobles, MNMISO Jan 2025target 2028
Battery storage project J3948, Posey County
Battery storage
200 MWIn study Posey, INMISO Mar 2025target 2030
Battery storage project J4123, Branch County
Battery storage
200 MWIn study Branch, MIMISO Sep 2025target 2030
Battery storage project J3881, Clay County
Battery storage
200 MWIn study Clay, ILMISO Feb 2025target 2030
Surplus; J1712
Battery storage
200 MWIn study Perry, ILMISO Apr 2025target 2027
Onshore wind project J3955, Lac Qui Parle County
Onshore wind
200 MWIn study Lac Qui Parle, MNMISO Apr 2025target 2030
Solar + storage project J4011, Miller County
Solar + storage
200 MWIn study Miller, ARMISO May 2025target 2029
Onshore wind project J4120, Lenawee County
Onshore wind
200 MWIn study Lenawee, MIMISO Sep 2025target 2030
Solar project J4092, Beauregard Parish County
Solar
200 MWIn study Beauregard Parish, LAMISO Oct 2025target 2030
Solar project J2848, Hamilton County
Solar
200 MWIn study Hamilton, INMISO Nov 2025target 2025
Solar + storage project J3979, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Solar project J3847, Jefferson County
Solar
200 MWIn study Jefferson, ILMISO Jan 2025target 2029
Battery storage project J4002, Edgar County
Battery storage
200 MWIn study Edgar, ILMISO Apr 2025target 2030
Onshore wind project J3928, Bay County
Onshore wind
200 MWIn study Bay, MIMISO Jan 2025target 2030
Onshore wind project J4129, Otter Tail County
Onshore wind
200 MWIn study Otter Tail, MNMISO Oct 2025target 2029
Battery storage project J4019, Calhoun County
Battery storage
200 MWIn study Calhoun, MIMISO May 2025target 2030
Solar project J3959, Grundy County
Solar
200 MWIn study Grundy, MOMISO Apr 2025target 2029
Surplus; J992
Battery storage
200 MWIn study Cass, INMISO Jun 2025target 2026
Solar + storage project J3058, Arkansas County
Solar + storage
200 MWIn study Arkansas, ARMISO Jul 2025target 2025
Solar project J4090, Schuyler County
Solar
200 MWIn study Schuyler, MOMISO Oct 2025target 2030
Onshore wind project J4099, Jackson County
Onshore wind
200 MWIn study Jackson, MNMISO Oct 2025target 2030
Battery storage project S1123, Beauregard Parish County
Battery storage
200 MWIn study Beauregard Parish, LAMISO Oct 2025target 2027
Solar project J4039, Montgomery County
Solar
200 MWIn study Montgomery, INMISO Jun 2025target 2030
Surplus; J1562
Battery storage
200 MWIn study Mississippi, ARMISO Jun 2025target 2027
Battery storage project J4137, Pulaski County
Battery storage
200 MWIn study Pulaski, ILMISO Sep 2025target 2030
Battery storage project J3947, Shelby County
Battery storage
200 MWIn study Shelby, ILMISO Mar 2025target 2030
Solar project J4003, Edgar County
Solar
200 MWIn study Edgar, ILMISO Apr 2025target 2030
Surplus; J1588
Battery storage
200 MWIn study Cass, NDMISO Mar 2025target 2028
Onshore wind project J3895, Muskegon County
Onshore wind
200 MWIn study Muskegon, MIMISO Feb 2025target 2028
Battery storage project J4173, Wapello County
Battery storage
199 MWIn study Wapello, IAMISO Oct 2025target 2028
Onshore wind project J4055, Ionia County
Onshore wind
198 MWIn study Ionia, MIMISO Aug 2025target 2027
Solar project J2750, Phillips County
Solar
198 MWIn study Phillips, ARMISO Aug 2025target 2026
Solar project J3908, St. Joseph County
Solar
196 MWIn study St. Joseph, MIMISO Mar 2025target 2025
Battery storage project J4155, Linn County
Battery storage
195 MWIn study Linn, IAMISO Oct 2025target 2029
Solar project J4044, Lenawee County
Solar
190 MWIn study Lenawee, MIMISO Aug 2025target 2028
Surplus; AMIL.TILT1-4
Solar
188 MWIn study Vermilion, ILMISO May 2025target 2027
Solar project J4023, Clay County
Solar
185 MWIn study Clay, INMISO Feb 2025target 2029
Solar project J3903, Mower County
Solar
185 MWIn study Mower, MNMISO Feb 2025target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)