United States › Grid › Interconnection queues › Arkansas
BATTERY STORAGE · MISOBattery storage project J4030, Faulkner County
Battery storage project J4030, Faulkner County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Faulkner County, Arkansas, connecting to ENTERGY ARKANSAS.
- PlanningQueued May 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4030
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- MAYFLOWER115KV
- Location
- Faulkner County, Arkansas
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 29 May 2025
- Proposed online date
- October 2029
Location
Marker shows the centre of Faulkner County; the queue data does not give exact sites.
Other requests in Faulkner County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem