🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Iowa

NUCLEAR · MISO

Replacing 200 MW of Solar with Nuclear; J1444

Replacing 200 MW of Solar with Nuclear; J1444 is a 200 MW nuclear request in interconnection study in the MISO interconnection queue, in Linn County, Iowa, connecting to ITC MIDWEST.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
R5069
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Duane Arnold (ARNOLD 5)
Location
Linn County, Iowa
Technology
Nuclear: 200 MW
Total requested
200 MW
Queue status
Active
Entered queue
26 August 2025
Proposed online date
December 2029

Location

Marker shows the centre of Linn County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Linn County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem