🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 440

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 440 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH1-235, Harrison County
Solar
8.0 MWWithdrawn / abandoned Harrison, OHPJM Sep 2021target 2023
Hydro project GI-1504, Lewis And Clark County
Hydro
8.0 MWWithdrawn / abandoned Lewis And Clark, MTWest Mar 2015target 2016
Solar project AG2-177, Sussex County
Solar
8.0 MWWithdrawn / abandoned Sussex, NJPJM Feb 2021target 2022
Coal project 56, Citrus County
Coal · Duke Energy Florida, LLC
8.0 MWWithdrawn / abandoned Citrus, FLSoutheast Jan 2007target 2012
NM Solar 1 LLC
Solar
8.0 MWWithdrawn / abandoned Bernalillo Cty, NMWest Sep 2011target 2014
Savage Mtn WF
Onshore wind
8.0 MWWithdrawn / abandoned Allegheny, PAPJM Jul 2003target 2011
Crystal Lake Substation - NG WMA Group 3
Battery storage
8.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2026
Solar project AF2-236, Crawford County
Solar
8.0 MWWithdrawn / abandoned Crawford, PAPJM Mar 2020target 2023
Gas project N04, New Castle County
Gas
8.0 MWWithdrawn / abandoned New Castle, DEPJM Aug 2004target 2004
Morris Solar Farm
Solar
8.0 MWWithdrawn / abandoned Sussex, NJPJM Mar 2011target 2014
Solar project AG2-256, Somerset County
Solar
8.0 MWWithdrawn / abandoned Somerset, NJPJM Mar 2021target 2022
Hydro project GEN-2015-004IS
Hydro
8.0 MWWithdrawn / abandoned SPP Nov 2015
Other project J3765, St. James Parish County
Other
8.0 MWWithdrawn / abandoned St. James Parish, LAMISO Apr 2024target 2024
Solar project 21772, Lenoir County
Solar
8.0 MWWithdrawn / abandoned Lenoir, NCSoutheast Oct 2018
Millstone Solar Farm
Solar
8.0 MWWithdrawn / abandoned Monmouth, NJPJM Oct 2010target 2016
Solar project AF2-167, Monmouth County
Solar
8.0 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2020target 2021
Geothermal project 1126, Klamath County
Geothermal
8.0 MWWithdrawn / abandoned Klamath, ORWest Apr 2019target 2020
Lancaster BESS
Battery storage · Saturn Energy Storage LLC
8.0 MWWithdrawn / abandoned Erie, NYNYISO Jan 2020
Solar project X2-001, Monmouth County
Solar
8.0 MWWithdrawn / abandoned Monmouth, NJPJM May 2011target 2012
Reddy I
Solar
8.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Solar project AG2-266, Madison County
Solar
8.0 MWWithdrawn / abandoned Madison, OHPJM Mar 2021target 2024
Solar project AH1-370, Greene County
Solar
8.0 MWWithdrawn / abandoned Greene, PAPJM Sep 2021target 2024
Other project O62, King And Queen County
Other
8.0 MWWithdrawn / abandoned King And Queen, VAPJM Jul 2005target 2006
Hornell Center 16 BESS
Battery storage · Sky Solar Inc.
8.0 MWWithdrawn / abandoned Allegany, NYNYISO Jul 2019
Sand Bluff Repower
Onshore wind
8.0 MWWithdrawn / abandoned Glasscock, TXERCOT Aug 2018
Solar project X3-013, Cape May County
Solar
8.0 MWWithdrawn / abandoned Cape May, NJPJM Aug 2011target 2012
Kimball DG Area Study
Solar + storage
7.9 MWWithdrawn / abandoned York, MEISO-NE May 2022target 2028
Onshore wind project GEN-2016-164, Day County
Onshore wind
7.9 MWWithdrawn / abandoned Day, SDSPP Nov 2016target 2017
Minotola 2 Solar Facility
Solar
7.9 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2010target 2018
Combined Reciprocating, Solar and Battery modification
Solar + storage
7.8 MWWithdrawn / abandoned Middlesex, MAISO-NE Sep 2018target 2022
Onshore wind project 857, Columbia County
Onshore wind
7.8 MWWithdrawn / abandoned Columbia, WAWest Mar 2017target 2019
Lemoore WWTP Solar
Solar
7.8 MWWithdrawn / abandoned Kings, CACAISO Mar 2011target 2013
Solar project X1-008, Warren County
Solar
7.8 MWWithdrawn / abandoned Warren, NJPJM Feb 2011target 2011
CMP County Road 115 kV SS - Winslow-Lakewood Areas Study
Solar + storage
7.8 MWWithdrawn / abandoned Kennebec, MEISO-NE Feb 2021target 2024
Wood River Substation - NG Western RI DG Area Study
Solar
7.8 MWWithdrawn / abandoned Washington, RIISO-NE Mar 2020target 2021
Solar project Y1-074, Summit County
Solar
7.8 MWWithdrawn / abandoned Summit, OHPJM Apr 2012target 2013
Group @ Berkshire 18C
Solar + storage
7.7 MWWithdrawn / abandoned Hampden, MAISO-NE Jan 2022target 2023
Solar project AH1-662, Kent County
Solar
7.7 MWWithdrawn / abandoned Kent, DEPJM Oct 2021target 2023
Group @ Podick - WMA ASO
Solar + storage
7.7 MWWithdrawn / abandoned Hampden, MAISO-NE Jan 2022target 2023
Solar project AD2-007, Surry County
Solar
7.6 MWWithdrawn / abandoned Surry, VAPJM Nov 2017target 2019
Solar project W3-131, Warren County
Solar
7.6 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2011
E Babe Smith Solar
Solar · Hwy 183 Solar LLC
7.6 MWWithdrawn / abandoned ERCOT Apr 2024target 2024
Solar project W2-051, Salem County
Solar
7.6 MWWithdrawn / abandoned Salem, NJPJM Jul 2010target 2011
Biomass
Other
7.6 MWWithdrawn / abandoned Cumberland, MEISO-NE Jun 2009target 2010
Gas project AD1-019, Atlantic County
Gas
7.6 MWWithdrawn / abandoned Atlantic, NJPJM May 2017target 2019
Solar project 31552, Horry County
Solar
7.6 MWWithdrawn / abandoned Horry, SCSoutheast Mar 2019
Onshore wind project 42, Meagher County
Onshore wind
7.5 MWWithdrawn / abandoned Meagher, MTWest Feb 2006
Solar project AG1-293, Crawford County
Solar
7.5 MWWithdrawn / abandoned Crawford, PAPJM Sep 2020target 2022
Solar project AG1-246, Fayette County
Solar
7.5 MWWithdrawn / abandoned Fayette, PAPJM Sep 2020target 2024
Gas project AA1-075, Atlantic County
Gas
7.5 MWWithdrawn / abandoned Atlantic, NJPJM Oct 2014target 2015
Page 440 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)