United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project Y1-074, Summit County
Solar project Y1-074, Summit County is a 7.8 MW solar request withdrawn in the PJM interconnection queue, in Summit County, Ohio, connecting to ATSI.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2012 (completed)
- Withdrawn / abandonedFeb 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Y1-074
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Martin 12kV
- Location
- Summit County, Ohio
- Technology
- Solar: 7.8 MW
- Total requested
- 7.8 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 30 April 2012
- Proposed online date
- November 2013
- Withdrawn
- February 2013
Location
Marker shows the centre of Summit County; the queue data does not give exact sites.
Other requests in Summit County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem