SOLAR Β· PJMBarberton Solar
Barberton Solar is a 14.0 MW solar request withdrawn in the PJM interconnection queue, in Summit County, Ohio, connecting to ATSI.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2011 (completed)
- Withdrawn / abandonedJun 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- X2-085
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- BarbertonβΓΓ¬Seiberling 23kV
- Location
- Summit County, Ohio
- Technology
- Solar: 14.0 MW
- Total requested
- 14.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 29 July 2011
- Proposed online date
- June 2014
- Withdrawn
- June 2014
Location
Marker shows the centre of Summit County; the queue data does not give exact sites.
Other requests in Summit County
- Gas project H029, Summit CountyGas Β· 268 MW Β· withdrawn
- Gas project X1-064A_AT13, Summit CountyGas Β· 268 MW Β· withdrawn
- Gas project J211, Summit CountyGas Β· 268 MW Β· withdrawn
- Solar project Y1-074, Summit CountySolar Β· 7.8 MW Β· withdrawn
- Other project Z2-020, Summit CountyOther Β· 0.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem