Minotola 2 Solar Facility

Minotola 2 Solar Facility is a 7.9 MW solar request withdrawn in the PJM interconnection queue, in Atlantic County, New Jersey, connecting to AEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2010 (completed)
  2. Withdrawn / abandonedMay 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
W4-027
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Minotola 12kV
Location
Atlantic County, New Jersey
Technology
Solar: 7.9 MW
Total requested
7.9 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
15 December 2010
Proposed online date
June 2018
Withdrawn
May 2016

Location

Marker shows the centre of Atlantic County; the queue data does not give exact sites.