πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

ONSHORE WIND Β· WEST

Onshore wind project 857, Columbia County

Onshore wind project 857, Columbia County is a 7.8 MW onshore wind request withdrawn in the West interconnection queue, in Columbia County, Washington, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
857
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Talbot substation
Location
Columbia County, Washington
Technology
Wind: 7.8 MW
Total requested
7.8 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
27 March 2017
Proposed online date
August 2019

Location

Marker shows the centre of Columbia County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Columbia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem