Onshore wind project 856, Columbia County

Onshore wind project 856, Columbia County is a 23.4 MW onshore wind request built and operating in the West interconnection queue, in Columbia County, Washington, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Mar 2017 (completed)
  2. ConsentedFeb 2018 (completed)
  3. Construction (completed)
  4. OperatingTarget Jul 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
856
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp Energy Supply Management
Connection point (POI)
Talbot substation
Location
Columbia County, Washington
Technology
Wind: 23.4 MW
Total requested
23.4 MW
Service type
Energy only (ERIS)
Study phase
IA signed 2/20/18
Queue status
Operational
Entered queue
27 March 2017
Agreement signed
20 February 2018
Proposed online date
July 2019

Location

Marker shows the centre of Columbia County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Columbia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem