300MW Lower Monumental-Starbuck

300MW Lower Monumental-Starbuck is a 300 MW onshore wind request withdrawn in the West interconnection queue, in Columbia County, Washington, connecting to RES North America.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G77
Grid region
West (non-ISO utilities)
Utility / transmission owner
RES North America
Developer
RES North America
Connection point (POI)
Lower Monumental-Starbuck 500 kV line.
Location
Columbia County, Washington
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
21 September 2001
Proposed online date
June 2004

Location

Marker shows the centre of Columbia County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Columbia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem