SOLAR Β· PJM

Solar project W3-131, Warren County

Solar project W3-131, Warren County is a 7.6 MW solar request withdrawn in the PJM interconnection queue, in Warren County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2010 (completed)
  2. Withdrawn / abandonedDec 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
W3-131
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Alpha #2 34.5kV
Location
Warren County, New Jersey
Technology
Solar: 7.6 MW
Total requested
7.6 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
29 October 2010
Proposed online date
November 2011
Withdrawn
December 2010

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Warren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem