Solar project AH1-235, Harrison County

Solar project AH1-235, Harrison County is a 8.0 MW solar request withdrawn in the PJM interconnection queue, in Harrison County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-235
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Kilgore Compressor Facility 138 kV
Location
Harrison County, Ohio
Technology
Solar: 8.0 MW
Total requested
8.0 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
December 2023
Withdrawn
December 2024

Location

Marker shows the centre of Harrison County; the queue data does not give exact sites.