United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 400

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 400 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AB1-133, Somerset County
Solar
20.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2015target 2016
Port Jeff -Mt. Sinai Energy Storage
Battery storage · Setauket Energy Storage, LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2019
Rich Road Storage
Battery storage · EDF Renewable Development, Inc
20.0 MWWithdrawn / abandoned St. Lawrence, NYNYISO Mar 2022
Solar project Q82, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Dec 2009target 2012
Onshore wind project G789, Pope County
Onshore wind
20.0 MWWithdrawn / abandoned Pope, MNMISO Apr 2007target 2010
Onshore wind project 324, Twin Falls County
Onshore wind
20.0 MWWithdrawn / abandoned Twin Falls, IDWest Mar 2010
Puckett Solar
Solar · Conti Enterprises, Inc.
20.0 MWWithdrawn / abandoned Chenango, NYNYISO Apr 2017
Solar project AE2-080, Surry County
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM Feb 2019target 2021
Holtsville Fuel Cell
Battery storage · FourGen LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jul 2019
Wiley Road
Solar
20.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2014target 2016
Solar project J309, Yellow Medicine County
Solar
20.0 MWWithdrawn / abandoned Yellow Medicine, MNMISO Nov 2013target 2016
Solar + storage project PIS065, Tooele County
Solar + storage · PacifiCorp
20.0 MWWithdrawn / abandoned Tooele, UTWest Jun 2024target 2028
Magruder Solar
Solar · Granada Solar, LLC
20.0 MWWithdrawn / abandoned Ulster, NYNYISO Jan 2018
Britton Road Solar Facility
Solar
20.0 MWWithdrawn / abandoned Morris, NJPJM Oct 2008target 2012
Solar project AH1-179, Shenandoah County
Solar · Valley Overlook Solar, LLC
20.0 MWWithdrawn / abandoned Shenandoah, VAPJM Aug 2021target 2022
Gas project AG1-132, Montgomery County
Gas
20.0 MWWithdrawn / abandoned Montgomery, OHPJM Sep 2020target 2021
Solar project Q321, Pinal County
Solar
20.0 MWWithdrawn / abandoned Pinal, AZWest Jan 2020target 2022
Solar project AE2-058, Northumberland County
Solar
20.0 MWWithdrawn / abandoned Northumberland, PAPJM Feb 2019target 2021
Solar project IC-545, Mitchell County
Solar
20.0 MWWithdrawn / abandoned Mitchell, GASoutheast Nov 2016
Full Circle
Onshore wind
20.0 MWWithdrawn / abandoned Kern, CACAISO Jun 2009target 2012
Battery storage project AA2-107, Dekalb County
Battery storage
20.0 MWWithdrawn / abandoned Dekalb, ILPJM Apr 2015target 2016
Epcal 1
Solar · sPower Development Company, LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jan 2018
Backbone Mountain Energy Storage
Battery storage
20.0 MWWithdrawn / abandoned Tucker, WVPJM Apr 2015target 2022
Solar project 270, Crockett County
Solar
20.0 MWWithdrawn / abandoned Crockett, TNSoutheast May 2015
Onshore wind project G684, Cottonwood County
Onshore wind
20.0 MWWithdrawn / abandoned Cottonwood, MNMISO Oct 2006target 2004
Battery storage project AG2-534, Warren County
Battery storage · Mansfield 3 LLC
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2025target 2022
Shawboro East Ridge Solar Park
Solar
20.0 MWWithdrawn / abandoned Currituck, NCPJM Aug 2014target 2019
Laneast Solar Farm (Fka Eastland Solar Farm)
Solar
20.0 MWWithdrawn / abandoned San Diego, CACAISO Sep 2010target 2016
Turner I Solar
Solar
20.0 MWWithdrawn / abandoned Henrico, VAPJM Aug 2017target 2022
Providence Heights WF
Onshore wind
20.0 MWWithdrawn / abandoned Bureau, ILPJM Dec 2005target 2010
Battery storage project AA1-117, Kankakee County
Battery storage
20.0 MWWithdrawn / abandoned Kankakee, ILPJM Oct 2014target 2016
Laurel West Solar Farm
Solar
20.0 MWWithdrawn / abandoned Kings, CACAISO Jul 2008target 2012
Honey Badger
Solar
20.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2014target 2016
Hebron Solar
Solar
20.0 MWWithdrawn / abandoned Wicomico, MDPJM Apr 2016target 2024
Hawkwind
Solar
20.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2014target 2016
Geothermal project Company LO, Pershing County
Geothermal
20.0 MWWithdrawn / abandoned Pershing, NVWest Sep 2021target 2025
Tehachapi Spindle
Battery storage
20.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2014
Solar project AA2-105, Halifax County
Solar
20.0 MWWithdrawn / abandoned Halifax, NCPJM Apr 2015target 2017
Solar project AD1-080, Rockingham County
Solar
20.0 MWWithdrawn / abandoned Rockingham, VAPJM Sep 2017target 2019
Lemoore Solar - C5
Solar
20.0 MWWithdrawn / abandoned Kings, CACAISO Apr 2012target 2014
Onshore wind project P24, Lee County
Onshore wind
20.0 MWWithdrawn / abandoned Lee, ILPJM Nov 2005target 2008
Onshore wind project J1817, Houghton County
Onshore wind
20.0 MWWithdrawn / abandoned Houghton, MIMISO Jul 2020target 2021
87677 Clifton Springs Standalone Storage
Battery storage · Nexamp Solar
20.0 MWWithdrawn / abandoned Ontario, NYNYISO Oct 2021
Solar project AA1-142, Wicomico County
Solar
20.0 MWWithdrawn / abandoned Wicomico, MDPJM Oct 2014target 2016
Mulberry Energy Storage Project
Battery storage · GSI Development Corp.
20.0 MWWithdrawn / abandoned Erie, NYNYISO Mar 2023
Solar project W1-088, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Solar project Y1-023
Solar
20.0 MWWithdrawn / abandoned OHPJM Feb 2012target 2013
Solar project Q151, Yavapai County
Solar
20.0 MWWithdrawn / abandoned Yavapai, AZWest Jun 2010target 2012
Blue Hill Solar
Solar · Blue Hill Solar Center, LLC
20.0 MWWithdrawn / abandoned Columbia, NYNYISO Aug 2014
Primrose Energy Storage Center
Battery storage
20.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2015target 2021
Page 400 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)