🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › North Carolina

SOLAR · PJM

Shawboro East Ridge Solar Park

Shawboro East Ridge Solar Park is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Currituck County, North Carolina, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2014 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AA1-049
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Shawboro-Sligo 230kV
Location
Currituck County, North Carolina
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
30 August 2014
Proposed online date
November 2019
Withdrawn
June 2017

Location

Marker shows the centre of Currituck County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Currituck County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem