SOLAR · PJMOak Trail Solar
Oak Trail Solar is a 50.0 MW solar request built and operating in the PJM interconnection queue, in Currituck County, North Carolina, connecting to Dominion.
Request details
- Queue ID
- AD2-160
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Hickory-Moyock 230kV
- Location
- Currituck County, North Carolina
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 26 March 2018
- Proposed online date
- July 2023
- Came online
- July 2023
Location
Marker shows the centre of Currituck County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Currituck County
- Shawboro SolarSolar · 150 MW · agreement signed
- Currituck SolarSolar · 80.0 MW · agreement signed
- Solar project AH1-033, Currituck CountySolar · 19.5 MW · in study
- Summit Farms Solar and Ranchland SolarSolar · 120 MW · built
- Oak Trail SolarSolar · 50.0 MW · built
- Battery storage project AH1-728, Currituck CountyBattery storage · 185 MW · withdrawn
- Onshore wind project W3-019, Currituck CountyOnshore wind · 150 MW · withdrawn
- Solar project AD2-181, Currituck CountySolar · 150 MW · withdrawn
- Wind + storage project AI1-169, Currituck CountyWind + storage · 150 MW · withdrawn
- Solar project AA1-133, Currituck CountySolar · 80.0 MW · withdrawn
- Solar project AA2-156, Currituck CountySolar · 80.0 MW · withdrawn
- Shawboro East Ridge Solar ParkSolar · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem