SOLAR Β· NYISO

Epcal 1

Epcal 1 is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2018 (completed)
  2. Withdrawn / abandonedApr 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
685
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
sPower Development Company, LLC
Connection point (POI)
Riverhead - Brookhaven 138kV
Location
Suffolk County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
19 January 2018
Withdrawn
April 2018

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem