Honey Badger

Honey Badger is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedJan 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1050
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Cameron Substation 69kV
Location
San Diego County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2014
Proposed online date
November 2016
Withdrawn
January 2016

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.