Battery storage project AG2-534, Warren County

Battery storage project AG2-534, Warren County is a 20.0 MW battery storage request withdrawn in the PJM interconnection queue, in Warren County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-534
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Developer
Mansfield 3 LLC
Connection point (POI)
Flanders-Pohatcong Mountain R722 34.5 kV
Location
Warren County, New Jersey
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
4 March 2025
Proposed online date
August 2022
Withdrawn
December 2025

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Warren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem