SOLAR · PJMBritton Road Solar Facility
Britton Road Solar Facility is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Morris County, New Jersey, connecting to JCPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2008 (completed)
- Withdrawn / abandonedAug 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- U3-032
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- JCPL
- Connection point (POI)
- Traynor 34.5kV
- Location
- Morris County, New Jersey
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 30 October 2008
- Proposed online date
- June 2012
- Withdrawn
- August 2018
Location
Marker shows the centre of Morris County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Morris County
- South CombeSolar · 15.4 MW · agreement signed
- Mount Olive Solar FarmSolar · 19.8 MW · built
- Berkshire SolarSolar · 1.6 MW · built
- Mt Hope Waterpower ProjectOther · 30.0 MW · withdrawn
- Battery storage project AG2-531, Morris CountyBattery storage · 20.0 MW · withdrawn
- Solar project AF1-145, Morris CountySolar · 20.0 MW · withdrawn
- Solar project AF1-008, Morris CountySolar · 20.0 MW · withdrawn
- Denville Storage FacilityBattery storage · 20.0 MW · withdrawn
- Mount Olive Solar FarmSolar · 17.0 MW · withdrawn
- Solar project V4-004, Morris CountySolar · 10.0 MW · withdrawn
- Solar project V3-005, Morris CountySolar · 10.0 MW · withdrawn
- Solar project W3-006, Morris CountySolar · 5.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem