South Combe

South Combe is a 15.4 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Morris County, New Jersey, connecting to JCPL.

Queue statusConsented
  1. PlanningQueued Sep 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AG1-191
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Chester-Pohatcong Mountain 34.5 kV
Location
Morris County, New Jersey
Technology
Solar: 15.4 MW
Total requested
15.4 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
17 September 2020
Proposed online date
December 2025

Location

Marker shows the centre of Morris County; the queue data does not give exact sites.