SOLAR Β· CAISO

Lemoore Solar - C5

Lemoore Solar - C5 is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2012 (completed)
  2. Withdrawn / abandonedMay 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
917
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Henrietta-GWF 115 kV Line;
Location
Kings County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 April 2012
Proposed online date
December 2014
Withdrawn
May 2013

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kings County