United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,141423.2 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,141 requests · page 4 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Lyra Solar
Solar + storage · Juno Solar 4
500 MWAgreement signed Borden, TXERCOT Mar 2025target 2027
Battery storage project C2-10, Salt Lake County
Battery storage · Oquirrh Energy Storage, LLC
500 MWAgreement signed Salt Lake, UTWest Apr 2022target 2031
Solar project GEN-2018-043, Burt County
Solar
500 MWAgreement signed Burt, NESPP May 2018target 2028
Onshore wind project C1-35, Carbon County
Onshore wind · Lucky Star Wind, LLC
500 MWAgreement signed Carbon, WYWest May 2021target 2028
Onshore wind project GI-2016-14, Cheyenne County
Onshore wind
500 MWAgreement signed Cheyenne, COWest Jul 20162020
Ironwood Solar
Solar + storage
500 MWAgreement signed Yuma, AZCAISO May 2017target 2026
Solar + storage project IA-PNM-2017-13, San Juan County
Solar + storage
500 MWAgreement signed San Juan, NMWest Oct 2017target 2020
Nuclear project C2-32, Lincoln County
Nuclear · US SFR Owner, LLC
500 MWAgreement signed Lincoln, WYWest Apr 2022target 2031
Antila Solar
Solar · Antila Solar LLC
500 MWAgreement signed Borden, TXERCOT Apr 2025target 2027
Lake Elsinore Advanced Pumped Storage Project
Battery storage
500 MWAgreement signed Riverside, CACAISO Jun 2005target 2028
Lyra Storage
Solar + storage · JUNO BESS I
500 MWAgreement signed Borden, TXERCOT May 2025target 2026
Battery storage project IC-1247, Heard County
Battery storage
500 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Fourth Quarter
Battery storage · Fourth Quarter BESS, LLC
500 MWAgreement signed Montgomery, MDPJM Oct 2020target 2030
Other project J1488, Randolph County
Other
500 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Juno 3 Solar
Solar · Juno Solar 3
500 MWAgreement signed Borden, TXERCOT Mar 2025target 2027
Calvada Springs Solar
Solar + storage
500 MWAgreement signed Inyo, CACAISO Apr 2020target 2027
Randolph Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
500 MWAgreement signed Halifax, VAPJM Dec 2019target 2032
Solar + storage project IA-PNM-2019-11, San Juan County
Solar + storage · 450CT 8ME
500 MWAgreement signed San Juan, NMWest Apr 2019target 2025
Goldback Solar Center
Battery storage
500 MWAgreement signed Ventura, CACAISO Apr 2019target 2026
Solar + storage project Company JK, Churchill County
Solar + storage
500 MWAgreement signed Churchill, NVWest Sep 2018target 2027
Solar + storage project J1586, Calhoun County
Solar + storage
499 MWAgreement signed Calhoun, MIMISO Jun 2020target 2025
Siete
Onshore wind · Apex Clean Energy
493 MWAgreement signed Webb, TXERCOT Oct 2018target 2028
Gas project GEN-2024-GR1, Oklahoma County
Gas
492 MWAgreement signed Oklahoma, OKSPP Jan 2024target 2026
Gas project GI-2006-1e, El Paso County
Gas
483 MWAgreement signed El Paso, COWest Jan 2006target 2007
Pluot
Solar + storage
479 MWAgreement signed Kings, CACAISO May 2016target 2026
Pomegranate
Solar + storage
479 MWAgreement signed Kings, CACAISO May 2016target 2025
Big SKY Solar
Solar + storage
476 MWAgreement signed Los Angeles, CACAISO Mar 2011target 2023
Coal project BHBE G11, Campbell County
Coal
475 MWAgreement signed Campbell, SDWest Sep 2011target 2011
Baker Branch Solar
Solar · Mockingbird Solar Center, LLC
469 MWAgreement signed Lamar, TXERCOT Mar 2020target 2026
Gas project GI-104, Payne County
Gas
460 MWAgreement signed Payne, OKSoutheast Jul 2022target 2026
Gas project GI-103, Creek County
Gas
460 MWAgreement signed Creek, OKSoutheast Jul 2022target 2027
Hollow Branch Creek Solar
Solar + storage · Hollow Branch Creek Solar LLC
460 MWAgreement signed Leon, TXERCOT Sep 2022target 2027
Gas project GI-121, Randolph County
Gas
460 MWAgreement signed Randolph, MOSoutheast May 2024target 2030
Gas project GI-101, Clinton County
Gas
460 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
NRG THW GT 345 (Tef)
Gas · NRG THW GT LLC
456 MWAgreement signed Harris, TXERCOT Nov 2022target 2026
Soleil Solar
Solar · Soleil Solar, LLC
452 MWAgreement signed Clay, TXERCOT Sep 2022target 2028
Zeissel Solar
Solar · ZSS Power, LLC
452 MWAgreement signed Knox, TXERCOT Feb 2022target 2028
Solar + storage project Q310, Yuma County
Solar + storage
450 MWAgreement signed Yuma, AZWest Aug 2019target 2023
Solar + storage project C1-11, Emery County
Solar + storage · Drunkards Wash Energy, LLC
450 MWAgreement signed Emery, UTWest Apr 2021target 2028
Cold Creek Solar 2
Solar + storage · Cold Creek Solar LLC
445 MWAgreement signed Schleicher, TXERCOT Dec 2023target 2028
NRG Greens Bayou 6 (TEF-Due Diligence)
Gas · NRG Greens Bayou 6 LLC
445 MWAgreement signed Harris, TXERCOT Aug 2022target 2028
Vast Sands Power II (TEF-Due Diligence)
Gas · Permian Power I LLC
440 MWAgreement signed Ward, TXERCOT Jul 2024target 2028
Vast Sands Power I (TEF -Due Diligence)
Gas · Permian Power I LLC
440 MWAgreement signed Ward, TXERCOT Jul 2024target 2028
Panhandle Flagship Solar 1
Solar + storage · Panhandle Solar Group Operating Company LLC
439 MWAgreement signed Carson, TXERCOT Mar 2023target 2027
Buffalo Creek
Solar · Lincoln Clean Energy Development
439 MWAgreement signed Fort Bend, TXERCOT Aug 2019target 2026
Battery storage project GEN-2020-057, Finney County
Battery storage
425 MWAgreement signed Finney, KSSPP Apr 2020target 2030
Solar project GEN-2020-058, Finney County
Solar
425 MWAgreement signed Finney, KSSPP Apr 2020target 2028
Whitehorse Wind
Onshore wind · MESQUITE STAR SPECIAL LLC
419 MWAgreement signed Fisher, TXERCOT Jun 20172020
Gamay Energy Storage
Battery storage · GAMAY ENERGY STORAGE LLC
419 MWAgreement signed Brazoria, TXERCOT Feb 2024target 2027
Sequoia II Solar
Solar · Deville Solar LLC
418 MWAgreement signed Callahan, TXERCOT Jan 2020target 2026
Page 4 of 43

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)