United States › Grid › Interconnection queues › Montana
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Montana — page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project 346, Golden Valley County Solar |
74.9 MW | Withdrawn / abandoned |
| Onshore wind project GI-1011, Blaine County Onshore wind |
70.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0930, Blaine County Onshore wind |
70.0 MW | Withdrawn / abandoned |
| Wind + storage project 170, Big Horn County Wind + storage |
62.5 MW | Withdrawn / abandoned |
| Onshore wind project 45, Jefferson County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Gas project 173, Lewis And Clark County Gas |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project 100-C, Big Horn County Onshore wind |
57.0 MW | Withdrawn / abandoned |
| Coal project 36, Rosebud County Coal |
56.0 MW | Withdrawn / abandoned |
| Onshore wind project 33, Wheatland County Onshore wind |
52.5 MW | Withdrawn / abandoned |
| Hydro project 83, Cascade County Hydro |
52.0 MW | Withdrawn / abandoned |
| Onshore wind project 30, Stillwater County Onshore wind |
50.4 MW | Withdrawn / abandoned |
| Solar project 279, Silver Bow County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project 299, Broadwater County Solar |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0203, Valley County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Solar project 313, Silver Bow County Solar |
50.0 MW | Withdrawn / abandoned |
| Battery storage project GEN-2019-024, Wibaux County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Battery storage project 448, Yellowstone County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Hydro project 82, Cascade County Hydro |
49.0 MW | Withdrawn / abandoned |
| Onshore wind project 140, Glacier County Onshore wind |
45.0 MW | Withdrawn / abandoned |
| Gas project G891, Fallon County Gas |
42.0 MW | Withdrawn / abandoned |
| Onshore wind project 113, Cascade County Onshore wind |
40.0 MW | Withdrawn / abandoned |
| Other project 119, Rosebud County Other |
36.0 MW | Withdrawn / abandoned |
| Coal project 37, Rosebud County Coal |
32.0 MW | Withdrawn / abandoned |
| Battery storage project 384, Yellowstone County Battery storage |
30.0 MW | Withdrawn / abandoned |
| Battery storage project 383, Missoula County Battery storage |
30.0 MW | Withdrawn / abandoned |
| Solar project 314, Silver Bow County Solar |
30.0 MW | Withdrawn / abandoned |
| Battery storage project 385, Lewis And Clark County Battery storage |
30.0 MW | Withdrawn / abandoned |
| Battery storage project 382, Gallatin County Battery storage |
30.0 MW | Withdrawn / abandoned |
| Battery storage project 386, Gallatin County Battery storage |
30.0 MW | Withdrawn / abandoned |
| Solar project 345, Yellowstone County Solar |
25.9 MW | Withdrawn / abandoned |
| Onshore wind project 210, Judith Basin County Onshore wind |
25.0 MW | Withdrawn / abandoned |
| Onshore wind project 209, Sweet Grass County Onshore wind |
25.0 MW | Withdrawn / abandoned |
| Onshore wind project 171, Judith Basin County Onshore wind |
25.0 MW | Withdrawn / abandoned |
| Onshore wind project 158, Cascade County Onshore wind |
24.3 MW | Withdrawn / abandoned |
| Onshore wind project 124, Cascade County Onshore wind |
24.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-1307, Valley County Onshore wind |
23.0 MW | Withdrawn / abandoned |
| Coal project 39, Yellowstone County Coal |
22.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-1303, Valley County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Battery storage project 395, Golden Valley County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 84, Teton County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 157, Sweet Grass County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 355, Teton County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Solar project 393, Golden Valley County Solar |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 117, Golden Valley County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Battery storage project 396, Golden Valley County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 60, Madison County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 288, Teton County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 155, Valley County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 88, Park County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 291, Big Horn County Onshore wind |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)379 · 30.8 GW
- SPP (Southwest Power Pool)12 · 2,303 MW
- MISO (Midcontinent)4 · 382 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)