United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

ONSHORE WIND Β· WEST

Onshore wind project 355, Teton County

Onshore wind project 355, Teton County is a 20.0 MW onshore wind request withdrawn in the West interconnection queue, in Teton County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
355
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
69kV Choteau - Pondera Oil Tap
Location
Teton County, Montana
Technology
Wind: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study Revised System Impact Study Facilities Study
Queue status
Withdrawn
Entered queue
28 September 2018
Proposed online date
October 2019

Location

Marker shows the centre of Teton County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Teton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem