πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

ONSHORE WIND Β· WEST

Onshore wind project 84, Teton County

Onshore wind project 84, Teton County is a 20.0 MW onshore wind request withdrawn in the West interconnection queue, in Teton County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
84
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
69kV between Big Sandy & Loma Substation
Location
Teton County, Montana
Technology
Wind: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
17 March 2008
Proposed online date
June 2009

Location

Marker shows the centre of Teton County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Teton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem