Onshore wind project 50, Teton County

Onshore wind project 50, Teton County is a 18.9 MW onshore wind request withdrawn in the West interconnection queue, in Teton County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
50
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Dutton 69kV Substation
Location
Teton County, Montana
Technology
Wind: 18.9 MW
Total requested
18.9 MW
Service type
Network resource (NRIS)
Study phase
Feasibility System Impact Study
Queue status
Withdrawn
Entered queue
29 June 2006
Proposed online date
December 2010

Location

Marker shows the centre of Teton County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Teton County