Onshore wind project 291, Big Horn County

Onshore wind project 291, Big Horn County is a 20.0 MW onshore wind request withdrawn in the West interconnection queue, in Big Horn County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
291
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
NWE's 69kV line near Toluca Siding
Location
Big Horn County, Montana
Technology
Wind: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
28 June 2016
Proposed online date
December 2017

Location

Marker shows the centre of Big Horn County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Big Horn County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem