COAL Β· WEST

Coal project GI-0306, Big Horn County

Coal project GI-0306, Big Horn County is a 109 MW coal request withdrawn in the West interconnection queue, in Big Horn County, Montana, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2003 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-0306
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Hardin
Location
Big Horn County, Montana
Technology
Coal: 109 MW
Total requested
109 MW
Service type
Energy only (ERIS)
Study phase
IAP
Queue status
Withdrawn
Entered queue
16 April 2003

Location

Marker shows the centre of Big Horn County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Big Horn County