Solar + storage project 428, Big Horn County

Solar + storage project 428, Big Horn County is a 80.0 MW solar + storage request withdrawn in the West interconnection queue, in Big Horn County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
428
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
69kV line in Hardin, MT
Location
Big Horn County, Montana
Technology
Solar: 80.0 MW Β· Battery
Total requested
80.0 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
12 May 2022
Proposed online date
December 2025

Location

Marker shows the centre of Big Horn County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Big Horn County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem