United States › Grid › Interconnection queues › Montana
COAL · WESTCoal project 5, Big Horn County
Coal project 5, Big Horn County is a 109 MW coal request built and operating in the West interconnection queue, in Big Horn County, Montana, connecting to NorthWestern Energy.
Request details
- Queue ID
- 5
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- Hardin Auto Substation
- Location
- Big Horn County, Montana
- Technology
- Coal: 109 MW
- Total requested
- 109 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study Facilities Study
- Queue status
- Operational
- Entered queue
- 19 April 2001
- Proposed online date
- April 2006
- Came online
- April 2006
Location
Marker shows the centre of Big Horn County; the queue data does not give exact sites.
Other requests in Big Horn County
- Solar project 419, Big Horn CountySolar · 300 MW · in study
- Hydro project T2-077, Bighorn CountyHydro · 8.0 MW · in study
- Solar project 193, Big Horn CountySolar · 3.0 MW · built
- Onshore wind project 937, Big Horn CountyOnshore wind · 250 MW · withdrawn
- Solar project 459, Big Horn CountySolar · 200 MW · withdrawn
- Solar + storage project 430, Big Horn CountySolar + storage · 200 MW · withdrawn
- Coal project GI-0306, Big Horn CountyCoal · 109 MW · withdrawn
- Onshore wind project 100-B, Big Horn CountyOnshore wind · 99.0 MW · withdrawn
- Onshore wind project 100-A, Big Horn CountyOnshore wind · 99.0 MW · withdrawn
- Solar + storage project 428, Big Horn CountySolar + storage · 80.0 MW · withdrawn
- Solar + storage project 1090, Big Horn CountySolar + storage · 80.0 MW · withdrawn
- Solar + storage project 1091, Big Horn CountySolar + storage · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem