πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

ONSHORE WIND Β· WEST

Onshore wind project 210, Judith Basin County

Onshore wind project 210, Judith Basin County is a 25.0 MW onshore wind request withdrawn in the West interconnection queue, in Judith Basin County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2015 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
210
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
NWE's Spion Kop 100kV Switchyard
Location
Judith Basin County, Montana
Technology
Wind: 25.0 MW
Total requested
25.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
13 August 2015
Proposed online date
December 2016

Location

Marker shows the centre of Judith Basin County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Judith Basin County