United States βΊ Grid βΊ Interconnection queues βΊ Montana
SOLAR Β· WESTSolar project 228, Judith Basin County
Solar project 228, Judith Basin County is a 3.0 MW solar request withdrawn in the West interconnection queue, in Judith Basin County, Montana, connecting to NorthWestern Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2015 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 228
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- Moccasin Substation
- Location
- Judith Basin County, Montana
- Technology
- Solar: 3.0 MW
- Total requested
- 3.0 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 23 November 2015
- Proposed online date
- November 2016
Location
Marker shows the centre of Judith Basin County; the queue data does not give exact sites.
Other requests in Judith Basin County
- Onshore wind project 317, Judith Basin CountyOnshore wind Β· 80.0 MW Β· built
- Onshore wind project 126, Judith Basin CountyOnshore wind Β· 24.0 MW Β· built
- Onshore wind project 135, Judith Basin CountyOnshore wind Β· 16.0 MW Β· built
- Onshore wind project 96, Judith Basin CountyOnshore wind Β· 305 MW Β· withdrawn
- Onshore wind project 97, Judith Basin CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project 210, Judith Basin CountyOnshore wind Β· 25.0 MW Β· withdrawn
- Onshore wind project 171, Judith Basin CountyOnshore wind Β· 25.0 MW Β· withdrawn
- Onshore wind project 337, Judith Basin CountyOnshore wind Β· 19.8 MW Β· withdrawn
- Onshore wind project 120, Judith Basin CountyOnshore wind Β· 10.0 MW Β· withdrawn
- Onshore wind project 122, Judith Basin CountyOnshore wind Β· 10.0 MW Β· withdrawn
- Onshore wind project 121, Judith Basin CountyOnshore wind Β· 10.0 MW Β· withdrawn
- Onshore wind project 125, Judith Basin CountyOnshore wind Β· 10.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem