United States › Grid › Interconnection queues › Montana

ONSHORE WIND · WEST

Onshore wind project 126, Judith Basin County

Onshore wind project 126, Judith Basin County is a 24.0 MW onshore wind request built and operating in the West interconnection queue, in Judith Basin County, Montana, connecting to NorthWestern Energy.

Queue statusOperating
  1. PlanningQueued Oct 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
126
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
100kV line West of Geyser
Location
Judith Basin County, Montana
Technology
Wind: 24.0 MW
Total requested
24.0 MW
Service type
NRIS and ERIS
Study phase
System Impact
Queue status
Operational
Entered queue
12 October 2010
Proposed online date
November 2011
Came online
November 2011

Location

Marker shows the centre of Judith Basin County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Judith Basin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem