Requests shown21646.0 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

216 requests · page 4 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Headwaters Wind Farm III
Onshore wind
100 MWPaused / redesign Randolph, INPJM Sep 2018target 2026
Solar + storage project AI1-081, Jay County
Solar + storage
100 MWIn study Jay, INPJM Jul 2022target 2026
Battery storage project J3166, Knox County
Battery storage
100 MWIn study Knox, INMISO Sep 2022target 2026
Battery storage project J2450, Tippecanoe County
Battery storage
100 MWIn study Tippecanoe, INMISO Sep 2022target 2026
Battery storage project AH2-233, Pulaski County
Battery storage
100 MWIn study Pulaski, INPJM Mar 2022target 2026
Riverstart Solar Park V
Solar
100 MWPaused / redesign Randolph, INPJM Mar 2019target 2026
Battery storage project AG2-248, Elkhart County
Battery storage · Amberjack Solar LLC
100 MWIn study Elkhart, INPJM Jan 2025target 2024
Solar project J1785, Laporte County
Solar
100 MWIn study Laporte, INMISO Jan 2022target 2024
Solar + storage project J2301, Vigo County
Solar + storage
100 MWIn study Vigo, INMISO Mar 2022target 2025
Solar + storage project AI1-009, Rush County
Solar + storage
100 MWIn study Rush, INPJM Apr 2022target 2026
Replacing 100 MW of Solar with storage; J1386
Battery storage
100 MWIn study Lake, INMISO Jul 2025target 2028
Solar project J2296, Sullivan County
Solar
100 MWIn study Sullivan, INMISO Mar 2022target 2025
Solar project J1736, Dubois County
Solar
100 MWIn study Dubois, INMISO Jun 2020target 2023
Onshore wind project J2048, Benton County
Onshore wind
100 MWIn study Benton, INMISO Mar 2022target 2025
Surplus; J1190
Battery storage
100 MWIn study Lagrange, INMISO Jul 2025target 2027
Solar project AH1-392, St. Joseph County
Solar · ibV Energy Partners LLC
90.0 MWIn study St. Joseph, INPJM Feb 2025target 2025
Gas project J3870, Vigo County
Gas
87.0 MWIn study Vigo, INMISO Dec 2024target 2002
Solar project AI2-115, Delaware County
Solar
84.0 MWIn study Delaware, INPJM Feb 2023target 2026
Battery storage project AH1-482, Pulaski County
Battery storage · Lightsource Renewable Energy Development, LLC
78.0 MWIn study Pulaski, INPJM Feb 2025target 2023
Battery storage project AH2-227, Jay County
Battery storage
75.0 MWIn study Jay, INPJM Mar 2022target 2026
Battery storage project AH1-302, Pulaski County
Battery storage · Bottlebrush Solar Energy LLC
75.0 MWIn study Pulaski, INPJM Feb 2025target 2025
Solar project J3896, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J4034, Vigo County
Solar
70.0 MWIn study Vigo, INMISO Jun 2025target 2030
Solar project J3925, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J2177, Tipton County
Solar
67.0 MWIn study Tipton, INMISO Aug 2021target 2024
Solar + storage project AG2-519, Delaware County
Solar + storage · Muncie Solar 1, LLC
66.5 MWIn study Delaware, INPJM Mar 2025target 2024
Surplus; J1067
Other
60.0 MWIn study White, INMISO May 20222024
Solar project J3897, Knox County
Solar
60.0 MWIn study Knox, INMISO Feb 2025target 2030
Dover Solar Facility
Solar
55.0 MWPaused / redesign Whitley, INPJM Mar 2019target 2026
Bluestem Solar
Battery storage · RWE Solar Development, LLC
55.0 MWIn study Laporte, INPJM Sep 2020target 2023
Gas project AG2-562, St. Joseph County
Gas · St. Joseph Energy Center, LLC
52.0 MWIn study St. Joseph, INPJM May 2025target 2022
Battery storage project AG2-370, Allen County
Battery storage · Tillman Storage LLC
50.0 MWIn study Allen, INPJM Mar 2025target 2024
Surplus; J1369
Other
50.0 MWIn study Dubois, INMISO Apr 2023target 2024
Battery storage project AG2-551, Randolph County
Battery storage · Riverstart Solar Park VI LLC
50.0 MWIn study Randolph, INPJM Feb 2025target 2024
Solar project AH2-223, Jay County
Solar
50.0 MWIn study Jay, INPJM Mar 2022target 2025
Battery storage project J3140, Porter County
Battery storage
50.0 MWIn study Porter, INMISO Sep 2022target 2026
Battery storage project J2045, Newton County
Battery storage
50.0 MWIn study Newton, INMISO Mar 2022target 2024
Solar project AH1-153, St. Joseph County
Solar · Dumont Solar, LLC
50.0 MWIn study St. Joseph, INPJM Mar 2025target 2025
Battery storage project S1126, Knox County
Battery storage
50.0 MWIn study Knox, INMISO Oct 2025target 2029
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO May 2022target 2028
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO Apr 2023target 2024
Battery storage project AG2-345, Fountain County
Battery storage · Dolphin Solar LLC
50.0 MWIn study Fountain, INPJM Feb 2025target 2024
Battery storage project AG2-014, White County
Battery storage · Black Prairie Storage LLC
50.0 MWIn study White, INPJM Feb 2025target 2023
Battery storage project AG2-492, White County
Battery storage · Black Prairie Storage II LLC
50.0 MWIn study White, INPJM Feb 2025target 2024
Battery storage project AH2-371, Jay County
Battery storage
50.0 MWIn study Jay, INPJM Mar 2022target 2026
Solar project AI2-161, Vermillion County
Solar
48.0 MWIn study Vermillion, INPJM Mar 2023target 2025
Solar project AI2-162, Whitley County
Solar
48.0 MWIn study Whitley, INPJM Mar 2023target 2025
Battery storage project J1861, Laporte County
Battery storage
45.0 MWIn study Laporte, INMISO Mar 2022target 2024
Solar project AI2-150, Huntington County
Solar
44.4 MWIn study Huntington, INPJM Feb 2023target 2025
Solar project AI2-421, Dekalb County
Solar
43.2 MWIn study Dekalb, INPJM Mar 2023target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)