United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in SPP (Southwest Power Pool) (2025 requests) β€” page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown26871.3 GW
Active in queue71.3 GW268 requests
Agreement signed0.0 MW0 requests
Withdrawn9926.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

268 requests Β· page 4 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2024-209, Clay County
Solar
199 MWIn study Clay, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-189, Ford County
Battery storage
199 MWIn study Ford, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-355, Lubbock County
Battery storage
199 MWIn study Lubbock, TXSPP Mar 2025target 2030
Battery storage project GEN-2024-120, Oklahoma County
Battery storage
199 MWIn study Oklahoma, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-352, Jackson County
Battery storage
199 MWIn study Jackson, MOSPP Mar 2025target 2030
Battery storage project GEN-2024-177, Bossier Parish County
Battery storage
199 MWIn study Bossier Parish, LASPP Mar 2025target 2029
Solar project GEN-2024-284, Mercer County
Solar
199 MWIn study Mercer, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-164, Murray County
Battery storage
199 MWIn study Murray, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-114, Jackson County
Solar + storage
199 MWIn study Jackson, ARSPP Mar 2025target 2028
Battery storage project GEN-2024-187, Mcclain County
Battery storage
199 MWIn study Mcclain, OKSPP Mar 2025target 2029
Wind + storage project GEN-2024-308, Woodward County
Wind + storage
199 MWIn study Woodward, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-250, Pittsburg County
Battery storage
199 MWIn study Pittsburg, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-320, Wyandotte County
Battery storage
199 MWIn study Wyandotte, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-184, Atoka County
Battery storage
199 MWIn study Atoka, OKSPP Mar 2025target 2029
Solar + storage project GEN-2024-272, Pratt County
Solar + storage
199 MWIn study Pratt, KSSPP Mar 2025target 2029
Battery storage project GEN-2024-167, Ray County
Battery storage
199 MWIn study Ray, MOSPP Mar 2025target 2030
Battery storage project GEN-2024-178, Harrison County
Battery storage
199 MWIn study Harrison, TXSPP Mar 2025target 2029
Battery storage project GEN-2024-318, Tulsa County
Battery storage
199 MWIn study Tulsa, OKSPP Mar 2025target 2028
Solar + storage project GEN-2024-218, Seward County
Solar + storage
199 MWIn study Seward, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-119, Cleveland County
Battery storage
199 MWIn study Cleveland, OKSPP Mar 2025target 2028
Solar + storage project GEN-2024-351, Lea County
Solar + storage
199 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-319, Wyandotte County
Battery storage
199 MWIn study Wyandotte, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-181, Greene County
Battery storage
199 MWIn study Greene, MOSPP Mar 2025target 2029
Battery storage project GEN-2024-245, Lincoln County
Battery storage
199 MWIn study Lincoln, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-121, Leavenworth County
Battery storage
199 MWIn study Leavenworth, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-186, Chaves County
Battery storage
199 MWIn study Chaves, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-118, Wagoner County
Battery storage
199 MWIn study Wagoner, OKSPP Mar 2025target 2028
Solar + storage project GEN-2024-267, Bryan County
Solar + storage
195 MWIn study Bryan, OKSPP Mar 2025target 2029
Solar project GEN-2024-158, Jackson County
Solar
190 MWIn study Jackson, OKSPP Mar 2025target 2029
Gas project ERAS-2025-003, Oklahoma County
Gas
186 MWIn study Oklahoma, OKSPP Sep 20252025
Battery storage project GEN-2025-SR14, Oklahoma County
Battery storage
183 MWIn study Oklahoma, OKSPP May 2025target 2030
Solar project GEN-2024-274, Harper County
Solar
175 MWIn study Harper, KSSPP Mar 2025target 2030
Solar project ERAS-2025-025, Caddo County
Solar
175 MWIn study Caddo, OKSPP Oct 2025target 2027
Battery storage project ERAS-2025-029, Wyandotte County
Battery storage
170 MWIn study Wyandotte, KSSPP Oct 2025target 2027
Solar + storage project GEN-2024-161, Jackson County
Solar + storage
170 MWIn study Jackson, OKSPP Mar 2025target 2030
Battery storage project GEN-2025-SR31, Madison County
Battery storage
170 MWIn study Madison, NESPP Nov 2025target 2026
Solar project GEN-2024-297, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-296, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-298, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-324, Chaves County
Battery storage
160 MWIn study Chaves, NMSPP Mar 2025target 2028
Solar + storage project GEN-2024-219, Murray County
Solar + storage
160 MWIn study Murray, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-360, Seminole County
Solar + storage
160 MWIn study Seminole, OKSPP Mar 2025target 2029
Solar + storage project GEN-2024-122, Marion County
Solar + storage
160 MWIn study Marion, TXSPP Mar 2025target 2029
Gas project ERAS-2025-014, Lea County
Gas
160 MWIn study Lea, NMSPP Oct 2025target 2029
Solar + storage project GEN-2024-265, Lea County
Solar + storage
155 MWIn study Lea, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-205, Stafford County
Solar + storage
155 MWIn study Stafford, KSSPP Mar 2025target 2029
Solar + storage project GEN-2024-261, Lea County
Solar + storage
150 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-325, Chaves County
Battery storage
150 MWIn study Chaves, NMSPP Mar 2025target 2028
Battery storage project GEN-2024-244, Texas County
Battery storage
150 MWIn study Texas, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-276, Shawnee County
Battery storage
150 MWIn study Shawnee, KSSPP Mar 2025target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)