United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) (2025 requests) β€” page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown390120.8 GW
Active in queue120.8 GW390 requests
Agreement signed180 MW1 requests
Withdrawn6222.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

390 requests Β· page 4 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J4201, Beauregard Parish County
Solar + storage
250 MWIn study Beauregard Parish, LAMISO Sep 2025target 2029
Battery storage project J3894, Lyon County
Battery storage
250 MWIn study Lyon, MNMISO Feb 2025target 2030
Battery storage project J4118, Mclean County
Battery storage
250 MWIn study Mclean, ILMISO Sep 2025target 2030
Solar project J4080, Jefferson County
Solar
250 MWIn study Jefferson, ARMISO Oct 2025target 2030
Solar project J3882, Crawford County
Solar
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Solar project J3911, Louisa County
Solar
250 MWIn study Louisa, IAMISO Feb 2025target 2030
FERMI Storage Project
Battery storage Β· DTE Electric
248 MWIn study Monroe, MIMISO Aug 2025target 2028
Solar project J4031, Scott County
Solar
245 MWIn study Scott, ILMISO May 2025target 2030
Solar project J3945, Washtenaw County
Solar
245 MWIn study Washtenaw, MIMISO Apr 2025target 2030
Solar project J4147, Clay County
Solar
245 MWIn study Clay, MNMISO Oct 2025target 2030
Solar project J4001, Marion County
Solar
245 MWIn study Marion, MOMISO Apr 2025target 2030
Solar project J3949, Scott County
Solar
245 MWIn study Scott, ILMISO Apr 2025target 2030
Solar project J4148, Clay County
Solar
245 MWIn study Clay, MNMISO Oct 2025target 2030
Solar project J3961, Lincoln County
Solar
245 MWIn study Lincoln, MNMISO Apr 2025target 2030
Battery storage project J4117, Goodhue County
Battery storage
240 MWIn study Goodhue, MNMISO Sep 2025target 2030
Onshore wind project J4068, Marshall County
Onshore wind
232 MWIn study Marshall, IAMISO Oct 2025target 2030
Onshore wind project J2104, Murray County
Onshore wind
230 MWIn study Murray, MNMISO Sep 2025target 2024
Solar project J4151, Redwood County
Solar
225 MWIn study Redwood, MNMISO Oct 2025target 2030
Solar project J4051, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project J4050, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project J4041, Menard County
Solar
220 MWIn study Menard, ILMISO Jun 2025target 2030
Solar project J3940, Isabella County
Solar
214 MWIn study Isabella, MIMISO Feb 2025target 2030
Sandhill Energy Storage
Battery storage Β· Xcel Energy
214 MWIn study Olmsted, MNMISO Aug 2025target 2025
Deckerville Solar Park Project
Solar Β· DTE Electric
213 MWIn study Sanilac, MIMISO Aug 2025target 2028
Battery storage project MPC04600, Eddy County
Battery storage
209 MWIn study Eddy, NDMISO Nov 2025target 2028
Amite Energy Storage II
Battery storage Β· NextEra Energy Resources Development, LLC
208 MWIn study Tangipahoa Parish, LAMISO Aug 2025target 2028
Bluejacket Solar
Solar Β· Hoosier Energy
205 MWIn study Bureau, ILMISO Nov 2025target 2028
Pumpkin Patch
Solar Β· Hoosier Energy
204 MWIn study Greene, ILMISO Nov 2025target 2028
Surplus; J449
Battery storage
202 MWIn study Mitchell, IAMISO Mar 2025target 2027
Solar project J2845, Freeborn County
Solar
200 MWIn study Freeborn, MNMISO Oct 2025target 2025
Surplus; J1190
Battery storage
200 MWIn study Clinton, IAMISO Jul 2025target 2026
Solar project J2753, East Carroll Parish County
Solar
200 MWIn study East Carroll Parish, LAMISO Aug 2025target 2026
Solar project J2322, Evangeline Parish County
Solar
200 MWIn study Evangeline Parish, LAMISO Nov 2025target 2025
Onshore wind project J3907, Stark County
Onshore wind
200 MWIn study Stark, ILMISO Mar 2025target 2030
Solar + storage project J3978, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Battery storage project J4119, Rankin County
Battery storage
200 MWIn study Rankin, MSMISO Sep 2025target 2029
Surplus; J834
Other
200 MWIn study Phillips, ARMISO Feb 2025target 2027
Battery storage project J4199, Fulton County
Battery storage
200 MWIn study Fulton, ILMISO Sep 2025target 2029
Battery storage project J2799, Van Buren County
Battery storage
200 MWIn study Van Buren, MIMISO Oct 2025target 2025
Onshore wind project J4193, Meeker County
Onshore wind
200 MWIn study Meeker, MNMISO Oct 2025target 2030
Solar + storage project J3980, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Solar project J3944, Bureau County
Solar
200 MWIn study Bureau, ILMISO Feb 2025target 2030
Solar project J4073, Coahoma County
Solar
200 MWIn study Coahoma, MSMISO Sep 2025target 2029
Solar project J3974, Jefferson County
Solar
200 MWIn study Jefferson, ARMISO Feb 2025target 2027
Surplus; J944
Battery storage
200 MWIn study New Madrid, MOMISO Aug 2025target 2028
Solar project J3880, Clay County
Solar
200 MWIn study Clay, ILMISO Feb 2025target 2030
Solar + storage project J2238, Maries County
Solar + storage
200 MWIn study Maries, MOMISO Jul 2025target 2024
Surplus; J416
Battery storage
200 MWIn study Franklin, IAMISO Aug 2025target 2026
Solar project J2538, Clark County
Solar
200 MWIn study Clark, INMISO Oct 2025target 2026
Solar project J4189, Sunflower County
Solar
200 MWIn study Sunflower, MSMISO Oct 2025target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)