🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Indiana, MISO — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown18241.7 GW
Active in queue41.7 GW182 requests
Agreement signed4,715 MW30 requests
Withdrawn36671.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

182 requests · page 4 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J903, Henry County
Solar
100 MWUnder construction Henry, INMISO Jun 2017target 2023
Solar project J2296, Sullivan County
Solar
100 MWIn study Sullivan, INMISO Mar 2022target 2025
Solar project J1369, Dubois County
Solar
100 MWAgreement signed Dubois, INMISO Apr 2019target 2025
Solar project J1392, Lagrange County
Solar
100 MWAgreement signed Lagrange, INMISO Apr 2019target 2025
Solar project J1736, Dubois County
Solar
100 MWIn study Dubois, INMISO Jun 2020target 2023
Onshore wind project J2048, Benton County
Onshore wind
100 MWIn study Benton, INMISO Mar 2022target 2025
Surplus; J1190
Battery storage
100 MWIn study Lagrange, INMISO Jul 2025target 2027
Solar project J847, Jasper County
Solar
90.0 MWUnder construction Jasper, INMISO Jun 20172023
Gas project J3870, Vigo County
Gas
87.0 MWIn study Vigo, INMISO Dec 2024target 2002
Solar project J3896, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J4034, Vigo County
Solar
70.0 MWIn study Vigo, INMISO Jun 2025target 2030
Solar project J3925, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J783, Spencer County
Solar
70.0 MWUnder construction Spencer, INMISO Nov 2016target 2021
Solar project J2177, Tipton County
Solar
67.0 MWIn study Tipton, INMISO Aug 2021target 2024
Surplus; J1067
Other
60.0 MWIn study White, INMISO May 20222024
Solar project J1387, Jasper County
Solar
60.0 MWAgreement signed Jasper, INMISO Apr 2019target 2024
Solar project J3897, Knox County
Solar
60.0 MWIn study Knox, INMISO Feb 2025target 2030
Surplus; J1369
Other
50.0 MWAgreement signed Dubois, INMISO May 2022target 2022
Surplus; J1369
Other
50.0 MWIn study Dubois, INMISO Apr 2023target 2024
Battery storage project J1272, Vanderburgh County
Battery storage
50.0 MWUnder construction Vanderburgh, INMISO Apr 2019target 2025
Solar project J1235, Knox County
Solar
50.0 MWAgreement signed Knox, INMISO Apr 2019target 2023
Battery storage project J3140, Porter County
Battery storage
50.0 MWIn study Porter, INMISO Sep 2022target 2026
Battery storage project J2045, Newton County
Battery storage
50.0 MWIn study Newton, INMISO Mar 2022target 2024
Battery storage project S1126, Knox County
Battery storage
50.0 MWIn study Knox, INMISO Oct 2025target 2029
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO May 2022target 2028
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO Apr 2023target 2024
Battery storage project J1861, Laporte County
Battery storage
45.0 MWIn study Laporte, INMISO Mar 2022target 2024
Onshore wind project J1470, Benton County
Onshore wind
30.0 MWAgreement signed Benton, INMISO Apr 20192020
Battery storage project J1323, Lagrange County
Battery storage
25.0 MWAgreement signed Lagrange, INMISO Apr 2019target 2025
Solar project J3208, Dubois County
Solar
10.0 MWIn study Dubois, INMISO Sep 2022target 2023
Battery storage project J1189, Brown County
Battery storage
5.0 MWUnder construction Brown, INMISO Mar 20182022
Surplus; Petersburg
Other
3.0 MWIn study Pike, INMISO May 2022target 2023
Page 4 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)