BATTERY STORAGE · MISO

Battery storage project J1189, Brown County

Battery storage project J1189, Brown County is a 5.0 MW battery storage request under construction in the MISO interconnection queue, in Brown County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusUnder construction
  1. PlanningQueued Mar 2018 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingMar 2022 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1189
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Crane Solar 69kV Substation
Location
Brown County, Indiana
Technology
Battery: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
12 March 2018
Proposed online date
January 2019
Came online
March 2022

Location

Marker shows the centre of Brown County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem