United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in the USA — page 32

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 32 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2019-044, Ford County
Solar
100 MWAgreement signed Ford, KSSPP May 2019target 2030
Solar project J552, Lee County
Solar
100 MWAgreement signed Lee, ARMISO Mar 20162024
Solar project J1248, Calhoun County
Solar
100 MWAgreement signed Calhoun, MIMISO Apr 2019target 2025
Solar project J909, Tangipahoa Parish County
Solar
100 MWUnder construction Tangipahoa Parish, LAMISO Jun 2017target 2022
Three Rivers Solar
Solar
100 MWAgreement signed Hancock, MEISO-NE Jan 2019target 2026
Solar project J1610, Sangamon County
Solar
100 MWIn study Sangamon, ILMISO Jun 2020target 2026
Solar project J2952, Chambers County
Solar
100 MWIn study Chambers, TXMISO Sep 2022target 2026
Solar project J3207, Starke County
Solar
100 MWIn study Starke, INMISO Mar 2022target 2024
Solar project J3916, Saline County
Solar
100 MWIn study Saline, ILMISO Oct 2024target 2030
Solar project J1430, Calhoun County
Solar
100 MWAgreement signed Calhoun, MIMISO Apr 20192023
Solar project J3685, Pike County
Solar
100 MWIn study Pike, ILMISO Apr 2024target 2028
Plano Skies Energy Center
Solar · Plano Skies Energy Center, LLC
100 MWIn study Kendall, ILPJM May 2019target 2022
Solar project J2055, Sheboygan County
Solar
100 MWIn study Sheboygan, WIMISO Aug 2021target 2026
Solar project J3439, Sherburne County
Solar
100 MWIn study Sherburne, MNMISO Apr 2024target 2026
Solar project J1239, Ouachita Parish County
Solar
100 MWUnder construction Ouachita Parish, LAMISO Apr 2019target 2024
Solar project J4037, Franklin County
Solar
100 MWIn study Franklin, IAMISO Jun 2025target 2030
Solar project J1778, Kenosha County
Solar
100 MWAgreement signed Kenosha, WIMISO Jun 2020target 2027
Solar project AI1-171, Whiteside County
Solar
100 MWIn study Whiteside, ILPJM Sep 2022target 2028
Elkhart County Solar Project
Solar
100 MWAgreement signed Elkhart, INPJM Mar 2019target 2026
Solar
Solar
100 MWIn study Rockingham, NHISO-NE Jul 2023target 2028
Solar project J2484, Monroe County
Solar
100 MWIn study Monroe, MIMISO Sep 2022target 2025
Riverside Solar
Solar · Riverside Solar, LLC
100 MWIn study Jefferson, NYNYISO Jun 2019target 2027
Solar project 919393, Wake County
Solar · Duke Energy Progress, LLC
100 MWIn study Wake, NCSoutheast Sep 2023
Solar project J1386, Lake County
Solar
100 MWAgreement signed Lake, INMISO Apr 2019target 2025
Flatrock Creek Solar II
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Gibson Solar I
Solar
100 MWAgreement signed King George, VAPJM Sep 2019target 2027
Solar project J1071, Oceana County
Solar
100 MWUnder construction Oceana, MIMISO Mar 2018target 2021
Bear Ridge Solar
Solar · Bear Ridge Solar, LLC
100 MWIn study Niagara, NYNYISO Mar 2018target 2027
Solar project J1313, Greene County
Solar
100 MWAgreement signed Greene, IAMISO Apr 2019target 2025
Solar project J3917, Columbia County
Solar
100 MWIn study Columbia, ARMISO Nov 2024target 2029
Solar project J680, Ashley County
Solar
100 MWUnder construction Ashley, ARMISO Jul 20162024
Solar project J2309, Murray County
Solar
100 MWIn study Murray, MNMISO Sep 2021target 2024
Solar project J2701, Jefferson Davis Parish County
Solar
100 MWIn study Jefferson Davis Parish, LAMISO Sep 2022target 2027
Madison County Solar
Solar
100 MWPaused / redesign Madison, INPJM Mar 2018target 2025
Solar project J1534, Olmsted County
Solar
100 MWIn study Olmsted, MNMISO Apr 2025target 2023
Solar project J1375, Muskegon County
Solar
100 MWUnder construction Muskegon, MIMISO Apr 2019target 2025
Solar project GEN-2019-009, Nemaha County
Solar
100 MWPaused / redesign Nemaha, NESPP Apr 2019target 2029
Solar project AI1-101, Lackawanna County
Solar
100 MWIn study Lackawanna, PAPJM Aug 2022target 2029
Solar project J1745, Winnebago County
Solar
100 MWAgreement signed Winnebago, WIMISO Jun 2020target 2028
Solar project J1445, Benton County
Solar
100 MWUnder construction Benton, MNMISO Apr 2019target 2025
Solar project J483, Liberty County
Solar
100 MWAgreement signed Liberty, TXMISO Sep 20152024
Blue Jay Solar
Solar
100 MWPaused / redesign Pulaski, VAPJM Mar 2018target 2025
Solar project 73, Adams County
Solar
100 MWIn study Adams, WAWest Oct 2018target 2020
Nuthatch Solar 5
Solar
100 MWAgreement signed Highland, OHPJM Sep 2019target 2030
Solar project Company 140, Clark County
Solar
100 MWAgreement signed Clark, NVWest Sep 2014target 2025
Solar project GI-86, Randolph County
Solar
100 MWAgreement signed Randolph, MOSoutheast Oct 2019target 2027
Solar project J1352, Montgomery County
Solar
100 MWAgreement signed Montgomery, MOMISO Apr 2019target 2024
Solar project GI-2024-17, Alamosa County
Solar
100 MWIn study Alamosa, COWest May 2024target 2030
Solar project 20-02261, Larimer County
Solar
100 MWIn study Larimer, COWest Feb 2020target 2023
Solar project J2233, Vermilion County
Solar
100 MWIn study Vermilion, ILMISO Jun 2022target 2024
Page 32 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)