🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2025 requests) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests · page 3 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project ERAS-2025-026, Comanche County
Gas
744 MWIn study Comanche, OKSPP Oct 2025target 2029
Gas project GEN-2024-299, Oklahoma County
Gas
744 MWIn study Oklahoma, OKSPP Mar 2025target 2032
Gas project ERAS-2025-024, Comanche County
Gas
744 MWIn study Comanche, OKSPP Oct 2025target 2029
Buffalo Jump Wind
Onshore wind · BOULEVARD ASSOCIATES, LLC
740 MWIn study Culberson, TXERCOT Nov 2025target 2029
Nuclear project J4040, Van Buren County
Nuclear
735 MWIn study Van Buren, MIMISO Jul 2025target 2030
Gas project GEN-2024-249, Pottawatomie County
Gas
721 MWIn study Pottawatomie, KSSPP Mar 2025target 2032
Gas project ERAS-2025-008, Sumner County
Gas
721 MWIn study Sumner, KSSPP Sep 2025target 2029
Solar + storage project Q2515, Maricopa County
Solar + storage
718 MWIn study Maricopa, AZWest Feb 2025target 2028
Gas project ERAS-2025-006, Reno County
Gas
718 MWIn study Reno, KSSPP Sep 2025target 2030
Meitner 2 Wind
Onshore wind · IP Meitner, LLC
709 MWIn study Gray, TXERCOT Jun 2025target 2028
Gas project J4190, Iberville Parish County
Gas
707 MWIn study Iberville Parish, LAMISO Oct 2025target 2030
Gas project 25-IC-1382, Mobile County
Gas
707 MWIn study Mobile, ALSoutheast Apr 2025target 2031
Gas project AG2-072, Spencer County
Gas · Bluegrass Power LLC
700 MWIn study Spencer, INPJM Feb 2025target 2026
Gas project 25RSC-001, Fayette County
Gas
692 MWIn study Fayette, TNSoutheast Jul 2025target 2031
Gas project GEN-2024-128, Caddo County
Gas
690 MWIn study Caddo, OKSPP Mar 2025target 2030
Solar + storage project Q114, Juab County
Solar + storage · Intermountain Power Agency
690 MWIn study Juab, UTWest Aug 2025target 2029
Gas project LGE-CS2025-002, Jefferson County
Gas
680 MWIn study Jefferson, KYSoutheast Nov 2025target 2031
Solar + storage project AH1-552, Prince George's County
Solar + storage · Chalk Point Steam, LLC
670 MWIn study Prince George's, MDPJM Mar 2025target 2025
Gas project J4159, Ottawa County
Gas
664 MWIn study Ottawa, MIMISO Aug 2025target 2028
Coleto Creek - Fuel Change Only
Gas · COLETO CREEK POWER LLC
655 MWIn study Goliad, TXERCOT Apr 2025target 2026
Battery storage project AH1-716, James City County
Battery storage · Cardinal Energy Storage East, LLC
650 MWIn study James City, VAPJM Apr 2025
Nuclear project J3932, Linn County
Nuclear
646 MWIn study Linn, IAMISO Mar 2025target 2029
Gas project J3084, Sullivan County
Gas
642 MWIn study Sullivan, INMISO Aug 2025target 2026
Commodus 2 Wind
Onshore wind · IP Blackwell II, LLC
642 MWIn study Swisher, TXERCOT Mar 2025target 2029
Solar + storage project T2-070, Harney County
Solar + storage
640 MWIn study Harney, ORWest Sep 2025target 2028
Malden BESS
Battery storage · NIPSCO
630 MWIn study Porter, INMISO Aug 2025target 2027
Howard Road BESS
Battery storage · Project Fast Flow LLC
618 MWIn study Bexar, TXERCOT Jul 2025target 2028
Symphony BESS
Battery storage · Symphony BESS, LLC
612 MWIn study Austin, TXERCOT Feb 2025target 2028
Moccasin Storage
Solar + storage · ENGIE IR Holdings LLC
603 MWIn study Jones, TXERCOT Jan 2025target 2028
Reunion Solar
Solar + storage · Reunion Solar, LLC
601 MWIn study Wilbarger, TXERCOT Mar 2025target 2028
Gas project 25-00419, Washoe County
Gas
600 MWIn study Washoe, NVWest Jul 2025target 2028
Onshore wind project GEN-2024-345, Nowata County
Onshore wind
600 MWIn study Nowata, OKSPP Mar 2025target 2030
Gas project 25-00428, Lincoln County
Gas
600 MWIn study Lincoln, NVWest Jul 2025target 2028
Geothermal project 25-00412, Humboldt County
Geothermal
600 MWIn study Humboldt, NVWest Jul 2025target 2032
Gas project T2-034, Sweetwater County
Gas · PacifiCorp
600 MWIn study Sweetwater, WYWest Sep 2025target 2030
Gas project ERAS-2025-017, Finney County
Gas
600 MWIn study Finney, KSSPP Sep 2025target 2029
Solar + storage project 25-00395, Washoe County
Solar + storage
600 MWIn study Washoe, NVWest Jul 2025target 2028
Gas project 37316, Laramie County
Gas
600 MWIn study Laramie, WYWest Jul 2025target 2027
Gas project T2-033, Sweetwater County
Gas · PacifiCorp
600 MWIn study Sweetwater, WYWest Sep 2025target 2030
Battery storage project 25-IC-1374, Hancock County
Battery storage
600 MWIn study Hancock, GASoutheast Apr 2025target 2029
Solar + storage project 25-00416, Humboldt County
Solar + storage
600 MWIn study Humboldt, NVWest Jul 2025target 2028
Geothermal project 25-00406, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2029
Gas project 25-00422, Lincoln County
Gas
600 MWIn study Lincoln, NVWest Jul 2025target 2028
Geothermal project 25-00409, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2033
Gas project T2-017, Converse County
Gas · PacifiCorp
600 MWIn study Converse, WYWest Aug 2025target 2029
Gas project 25-00430, Storey County
Gas
570 MWIn study Storey, NVWest Jul 2025target 2030
RAYBURN ENERGY STATION II Gas (TEF-Due Diligence)
Gas · Rayburn Energy Station LLC
570 MWIn study Grayson, TXERCOT Jan 2025target 2028
Rio Vista Solar
Solar + storage · Rio Vista Solar, LLC
554 MWIn study Pecos, TXERCOT Jun 2025target 2028
Miller Bend Energy BESS
Solar + storage · Miller Bend Energy
548 MWIn study Young, TXERCOT Dec 2025target 2029
Solar project J4102, Cass County
Solar
539 MWIn study Cass, MIMISO Oct 2025target 2029
Page 3 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)